Important Information
This website uses cookies. By using this website you accept the use of cookies. Learn more.
applicable starting with 1 June 2025
On 29 May 2025, the ANRE Order no. 20/2025 for amending and supplementing certain ANRE orders regarding the connection of users to the public energy grid (“Order no. 20/2025”) was published in the Official Gazette and entered into force on 1 June 2025.
The Order no. 20/2025 amended the following ANRE orders:
We will present below a detailed summary of the main amendments brought to the Connection Regulation.
1. The possibility of updating the ATR by including the operational power limitations (“Grid Curtailments”) is now officially recognized
Grid Connection Approvals (“ATRs”) that were still valid on 1 June 2025[1] may now be updated upon the user’s request. Following such a request, the updated ATR must be issued within 30 days, and, where applicable, an addendum to the Grid Connection Agreement (“GCA”) will be concluded.
This update is particularly relevant for ATRs issued without considering grid curtailments, especially those released before or shortly after the introduction of operational limitations in June 2022. Until now, it was generally understood that ATR updates to reflect curtailments were only possible if the conditions under the transitory provisions of ANRE Order 81/2022 were met. In practice, however, some grid operators allowed such updates, while others did not, leading to inconsistent treatment across projects.
Although this express provision comes with a significant delay, it may still offer positive outcomes for older projects, particularly those facing high reinforcement costs under N-1 scenarios.
2. The Grid Curtailments are now qualified as grid connection works (until now, they were qualified as grid reinforcement works)
This amendment has drawn criticism from the industry during the public consultation phase, as it places the operation and maintenance (“O&M”) responsibilities and the related costs and risks on the investors, even when the Grid Curtailment installations are located within the grid operator’s facilities.
In an attempt to address some of the concerns, ANRE has introduced a provision stating that the exploitation convention (to be signed between the user and the grid operator for the use of Grid Curtailments) must include the user’s right to access the relevant installations for O&M purposes, even if they are situated within the operator’s infrastructure.
3. Upon the calculations under the solution study (“SS”), projects are considered in the chronological order in which the complete documentation is submitted
ANRE considered it useful to specifically regulate a practice that was already in place, but which was not always applied uniformly.
As such, when determining the input data for the SS, the following projects within the same network area are taken into account in order to assure the observance of the chronological order of the grid connection applications:
These rules also apply to users who submitted connection requests but had not yet signed contracts for the preparation of the SS until 1 June 2025.
4. User input process prior to the SS approval meeting
ANRE once again considered it necessary to formally regulate a practice that had been applied until now, but inconsistently and without clear procedural guidance.
By introducing specific deadlines, the regulation ensures that users are given adequate time to review the solution study and raise any objections:
This clarification aims to standardize the process across all network operators, enhancing transparency and ensuring that users can participate meaningfully in the evaluation of connection solutions.
5. Financial guarantee submission and ATR issuance deadlines
Since the introduction on 2 August 2024 of the financial guarantee requirement before the issuance of the ATR, its effectiveness in preventing non-committed investors from blocking grid capacity has been limited, mainly due to the lack of clear deadlines for submitting the guarantee and issuing the ATR.
To address this gap, ANRE has now introduced specific deadlines aimed at reinforcing the credibility and efficiency of the connection process:
6. Grid Connection Agreement (“GCA”) signing process
Aware that, in practice, delays in signing grid connection agreements often occur — caused by both users and network operators — ANRE considered it necessary to introduce a clear and enforceable timeline for initiating and completing the contract signing process.
This regulatory intervention aims to ensure predictability, reduce procedural bottlenecks, and promote consistent application across all network operators:
While the new rules introduce stricter deadlines for users, it remains unclear what happens if the grid operator fails to meet its own deadlines. Notably, there is no express provision allowing the 12-month deadline for signing the GCA to be extended in cases where the delay is caused by the operator’s fault, including in case of lack of cooperation or failure to negotiate the GCA terms.
In such situations, it may be assumed that the user has grounds to file a formal complaint with ANRE. If the complaint is found to be justified, ANRE should require the operator to issue the signed draft agreement even after the expiry of the ATR validity, as the Connection Regulation only exempts the operator from this obligation when the user fails to meet its own deadlines.
Although not explicitly regulated, such complaint mechanism could serve as a practical safeguard, and hopefully, a sufficient incentive for grid operators to comply with their procedural obligations.
7. Amendments of the GCA
The parties to a GCA may amend or extend it by mutual agreement through addenda or, as applicable, by following the below rules:
The new provisions also apply to GCA extension requests submitted before 1 June 2025.
For GCAs set to expire within 30 days from the same date, the standard deadlines under letters c) and d) above are reduced accordingly, to ensure that the extension process, including the submission of the financial guarantee, can still be completed in time.
These rules respond to a pressing issue in practice: congested grid capacity is often blocked by projects with low implementation prospects. ANRE’s initiative aims to introduce a uniform and enforceable framework for GCA extensions across all grid operators, helping to clear capacity for viable projects.
Moreover, this clarification is particularly relevant in light of Transelectrica’s salutary but too strict attempt to stop unjustified GCA extension requests, through an internal regulation[4] issued in December 2024. It should be interpreted that said internal rule is no longer applicable starting with 1 June 2025, as the currently applicable Connection Regulation (being a higher-ranking legal instrument) takes precedence since it regulates the same subject matter.
8. Trafo/ Connection Station ≥ 110 kV specific regulations
Annex 5 of the Connection Regulation was amended, in such a way as to include explicit reference that it applies also for single-user connection solutions (not only to shared connection solutions for 2 or more users, as the previous text seemed to suggest).
As such, for the Trafo and/or Connection Stations ≥ 110 kV, irrespective of whether they are single-user or shared connection solutions, the following rules apply:
While this approach might have seemed more appropriate for connection stations (given their proximity to the grid connection point and potential classification as part of the grid operator’s infrastructure) it ultimately supports long-term project planning, particularly in terms of costs, risks, and liabilities. As such, under this framework, the O&M and associated responsibilities for transformer stations and their connection lines up to the grid point will rest with the grid operator, even when the station is located within or in the immediate vicinity of the PV or wind park.
It remains unclear whether connection stations were intentionally left excluded from this classification or if their omission was unintentional.
[1] i.e. upon the date when the Order 20/2025 entered into force
[2] The request must be signed and accompanied by the documents listed in Article 36 para (1) of the Connection Regulation.
[3] Regulated under Order 105/2022
[4] Which, among others, regulated that the user had to provide (i) proof of payment of at least 25% of the equipment cost or proof of the executing at least 10% of the user’s installation and (ii) monthly reports on the execution progress in accordance with the execution schedule enclosed to the agreement.