The Ministry of Energy recently published for public consultation the draft Government Decision for the implementation and operation of the Contracts for Difference (CfD) support mechanism for low carbon technologies[1].
Through this enactment, the Romanian Government establishes the general legal framework governing the implementation and operation of the support mechanism through contracts for difference meant to foster priority investment in technologies for the production of energy from onshore and offshore wind resources, solar photovoltaic resources, hydro resources, nuclear resources, hydrogen and energy storage systems.
To this end, the underlying public authority shall prepare the CfD State aid or ad hoc CfD State aid schemes which may require authorisation by the European Commission. The CfD contracts shall be awarded by way of CfD competitive tender organised by Transelectrica S.A[2]., whilst in case of ad hoc CfD State aid scheme, the same may be awarded for power generation projects for which a competitive selection process cannot be applied. The terms and conditions of ad-hoc CfD contracts will be determined by direct negotiation and are subject to the European Commission's State aid approval decision.
The price for a CfD contract is determined by CfD tender, while for ad hoc CfD State aid, the price is determined by negotiation. The reference price is set by OPCOM[3] in accordance with the formula from the CfD contract and the methodology issued by the market energy regulator[4]. OPCOM is also responsible for calculating and processing payments for the CfD difference to CfD beneficiaries based on the balance between the call price and the reference price from the CfD contract. CfD beneficiaries receive no CfD difference payment for the electricity injected in the National Electricity System if reference price corresponding to the respective production is negative.
Pursuant to the Information paper for tenderers[5], the CfD scheme will involve two rounds of tenders, each with separate bids for eligible power generation technologies - onshore wind and solar PV - with a total capacity of 5,000 MW.
The total capacities targeted are as follows: (i) installed capacity of 1,000 MW for onshore wind power generation and 1,000 MW for solar PV power generation respectively, both following the first round of tenders to take place by the end of 2023; and (ii) installed capacity of 1,500 MW for onshore wind power generation and 1,500 MW for solar PV power generation respectively, both as a result of the second tender round to be held in the first half of 2025.
The key terms of the CfD scheme feature the following:
This information paper outlines also the key tender requirements, while further details will be provided in the tender opening order, as follows:
On the other hand, the project must meet the following requirements:
The funding of the CfD support scheme is provided through the CfD contribution collection mechanism applied to all final consumers – starting with January 1, 2024 - and/or through non-reimbursable EU funds.
Where a CfD contract includes provisions to address any additional costs stemming from changes in primary or secondary legislation, such costs will be covered by adjusting the call price in the CfD contract, but only to the extent that a significant change has occurred, additional costs have incurred, or to the extent that such costs have been finally determined in accordance with the provisions of the CfD contract.
*****
This article contains general information and cannot be considered qualified legal advice.
[1] The draft is available at https://energie.gov.ro/wp-content/uploads/2023/08/Hotararea-de-Guvern-CfD-7-august-Fin.pdf. An English version of the same is available at https://www.mprpartners.com/expertise/energy-natural-resources/?pub
[2] The Transmission System Operator, https://www.transelectrica.ro/en/web/tel/home
[3] Electricity and Natural Gas Market Operator "OPCOM" S.A., https://www.opcom.ro/acasa/en
[4] The National Energy Regulatory Authority, https://anre.ro/en/
[5] It is available at https://energie.gov.ro/wp-content/uploads/2023/08/Nota-informativa-pentru-ofertanti_CfD-pentru-regenerabile_04.08.2023.pdf. An English version of the same is available at https://www.mprpartners.com/expertise/energy-natural-resources/?pub